Week 6-8

November 24-December 13

Work has been progressing, but we're getting to a stage where the changes day-to-day are no longer dramatic. Unfortunately, as expected we have run into some serious problems with the structure of the house. The garage has required extensive repair due to poor framing and rotting wood. We are very lucky that we are doing this on our own timetable and not because of disaster.

No new exterior picture. It's pretty much the same as in week 5 except all the siding and brick is gone and replaced by Tyvek wrap.

We have stairs!

121102_4

Notice the floor to ceiling pink tiles in the bathroom at the end of the hall. Ugh!! I will celebrate when that bathroom is gutted in a few months.